100 Million Investment in Langfang Project

2018-12-04     Source:未知

Langfang city is the provincial municipality of Hebei Province, which is located in the middle and lower reaches of Haihe basin and in the hinterland around Bohai. It enjoys the reputation of “pearl of Beijing-Tianjin corridor”. However, in recent years, with the rapid development of urban economy, the speed of urban environmental treatment cannot keep up with the development of the city. The canal pollution in the central urban area of Langfang city is very serious, which has become the trouble of the citizens. So canal pollution control is very imminent.


The release of the general contract of EPC project of canal treatment in the central urban area of Langfang city indicates that the action of canal pollution control has officially started. It is expected to invest 100 million to comprehensively treat several water areas in the central urban area, restore the clarity of the canals, and create a good environment of clear water and blue sky for the citizens. This time, our company has made a reasonable and efficient comprehensive canal treatment solution after on-site investigation and detection of canal pollution since winning the bid.


Project profile

Canals in the central urban area are very dense. Due to the imperfection of sewage discharge system and inadequate pollution interception, a large amount of sewage is discharged into the river channel, which worsens the water quality. In addition, the discharge of municipal solid waste and sewage makes the water in the canal black and smelly, and the sediment deposition is very serious.

Main equipment

There are special rapid press for dredging of rivers and lakes, garbage sorting screen, concentration tank lifting pump, sludge return pump, conditioning tank, feed plunger pump and other related equipment.

On-site situation of canal management


(River dredging project implementation scope of six main canal)


(Location map of box culvert of eight main canal and status quo of sediment pollution)


(Implementation scope of sediment microbial remediation project in six main canal)

Project management plan

The treatment project adopts the water ecological restoration technology system composed of river sediment improvement technology and water ecosystem construction technology to carry out water ecological restoration for the river basin water. This system technology can effectively absorb the internal source pollution and non-point source pollution (atmospheric precipitation, rainfall, surface runoff, garbage leaves and other non-point source pollution), and restore the natural balance of water ecosystem.

First, river dredging

The river is dammed in sections. It is divided into 5 sections according to the actual length of the river. Among them, the first section is designated as the first pool, and this section is set as a temporary sludge storage tank. All the sludge in the last four sections is cleared to the first section, and then the sludge is transported from the tank to a conditioning tank in the site on the shore for conditioning, and then transported to a river special press for pressing treatment.


Second, the sediment dewatering

Because of the high water content of the bottom sludge of the river and canal, a process with obvious reduction effect is needed to dewater and facilitate subsequent transportation and disposal. Therefore, the treatment process adopted by the project should be characterized by high efficiency and energy saving, low water content of the sludge after treatment and convenience of subsequent resource utilization. Therefore, we decided to adopt mechanical dehydration integration technology (super high pressure filter press dewatering), which can be effectively coupled with sediment dredging, and has the advantages of rapid dewatering of sediment, less sediment transport cost and management cost.


In recent years, more and more attention has been paid to the problem of water pollution. Under the call on of relevant government policies, black and smelly water treatment is being carried out across the country. With our own technical advantages and innovative spirit, we have launched a comprehensive river and lake management solutions. At present, the project cases are all over the country. The signing of this project not only shows our excellent achievements in the comprehensive treatment of black and smelly water bodies, but also shows the customer's affirmation of our products and solutions. As a provider of environmental protection products and technical solutions deeply rooted in wastewater and sludge industry, we will continue to innovate and develop, constantly improve product quality and service, and solve environmental problems for our customers.